Canal — progress

As of 13 Aug 2026 · this period: since v1.2.0 (11 Jun 2026)

20% of scope is unsized, counted at the median 3 points, and drawn hatched as estimated.

Complete
80%
37 of 46 points
Delivered this period
4
16 → 37 complete
Scope change this period
+3
1 added · 0 taken out
In progress
0
9 not started · 5 parked

Work complete against scope

This period0122436486015 Jun22 Jun29 Jun6 Jul13 Jul20 Jul27 Jul3 Aug10 Augv1.3.0 · 9 Jul 2026, 09:00 UTCv1.4.0 · 6 Aug 2026, 09:00 UTCv1.3.0v1.4.0since v1.2.05 parkedScope 4637 complete11 Jun 2026Night lights planned, then parkedComplete16In progress8Not started19Scope43Parked518 Jun 2026Bottom paddles replacedComplete24In progress0Not started19Scope43Parked525 Jun 2026Start the balance beams and cancellationsComplete24In progress5Not started14Scope43Parked52 Jul 2026Sensor import designed; dashboard addedComplete24In progress5Not started17Scope46Parked59 Jul 2026Booking cancellations doneComplete26In progress3Not started17Scope46Parked516 Jul 2026Start the sensor importComplete26In progress11Not started9Scope46Parked523 Jul 2026Water level alerts designedComplete26In progress11Not started9Scope46Parked530 Jul 2026Balance beams doneComplete29In progress8Not started9Scope46Parked56 Aug 2026Signage designedComplete29In progress8Not started9Scope46Parked513 Aug 2026Sensor import doneComplete37In progress0Not started9Scope46Parked5
Show on the charts

Select a key entry to hide or show it on every chart.

Data as a table
WhenChangeCompleteIn progressNot startedScopeParked
2 Mar 2026Plan the first lock works0034340
8 Mar 2026Design gate repairs and the booking calendar0034340
12 Mar 2026Start gate repairs0529340
19 Mar 2026Start the booking calendar01024340
26 Mar 2026Gate repairs done5524340
2 Apr 2026Booking cancellations planned5526360
9 Apr 2026Slot booking calendar done10026360
16 Apr 2026Design notifications and the stoppage plan10026360
23 Apr 2026Water level alerts and towpath signage added10331440
30 Apr 2026Winter stoppage plan done12329440
7 May 2026Captain notifications done15029440
14 May 2026Online slot payments planned15038530
21 May 2026Start paddle replacement15830530
28 May 2026Lubrication schedule done16829530
4 Jun 2026Drop online payments16819430
11 Jun 2026Night lights planned, then parked16819435
18 Jun 2026Bottom paddles replaced24019435
25 Jun 2026Start the balance beams and cancellations24514435
2 Jul 2026Sensor import designed; dashboard added24517465
9 Jul 2026Booking cancellations done26317465
16 Jul 2026Start the sensor import26119465
23 Jul 2026Water level alerts designed26119465
30 Jul 2026Balance beams done2989465
6 Aug 2026Signage designed2989465
13 Aug 2026Sensor import done3709465

Delivered this period · 4 (21 pts)

  • Lock sensor import · 8 pts
  • Balance beam refurbishment · 3 pts
  • Booking cancellations · 2 pts
  • Replace the bottom paddles · 8 pts

Added this period · 1 (3 pts)

  • Sensor dashboard for lock keepers

Taken out this period · 0

Nothing taken out of scope.

Workstreams

Same scale and key as above. A work item in two workstreams appears in both.

Sensors 8 of 14 complete

0102011 Jun 2026Complete0In progress0Not started11Scope1118 Jun 2026Complete0In progress0Not started11Scope1125 Jun 2026Complete0In progress0Not started11Scope112 Jul 2026Complete0In progress0Not started14Scope149 Jul 2026Complete0In progress0Not started14Scope1416 Jul 2026Complete0In progress8Not started6Scope1423 Jul 2026Complete0In progress8Not started6Scope1430 Jul 2026Complete0In progress8Not started6Scope146 Aug 2026Complete0In progress8Not started6Scope1413 Aug 2026Complete8In progress0Not started6Scope14
  • Water level alerts
  • Sensor dashboard for lock keepers

Booking 10 of 10 complete

0102011 Jun 2026Complete8In progress0Not started2Scope1018 Jun 2026Complete8In progress0Not started2Scope1025 Jun 2026Complete8In progress2Not started0Scope102 Jul 2026Complete8In progress2Not started0Scope109 Jul 2026Complete10In progress0Not started0Scope1016 Jul 2026Complete10In progress0Not started0Scope1023 Jul 2026Complete10In progress0Not started0Scope1030 Jul 2026Complete10In progress0Not started0Scope106 Aug 2026Complete10In progress0Not started0Scope1013 Aug 2026Complete10In progress0Not started0Scope10

All delivered.

Gates 10 of 10 complete

0102011 Jun 2026Complete7In progress0Not started3Scope10Parked518 Jun 2026Complete7In progress0Not started3Scope10Parked525 Jun 2026Complete7In progress3Not started0Scope10Parked52 Jul 2026Complete7In progress3Not started0Scope10Parked59 Jul 2026Complete7In progress3Not started0Scope10Parked516 Jul 2026Complete7In progress3Not started0Scope10Parked523 Jul 2026Complete7In progress3Not started0Scope10Parked530 Jul 2026Complete10In progress0Not started0Scope10Parked56 Aug 2026Complete10In progress0Not started0Scope10Parked513 Aug 2026Complete10In progress0Not started0Scope10Parked5

All delivered.

Paddles 9 of 9 complete

0102011 Jun 2026Complete1In progress8Not started0Scope918 Jun 2026Complete9In progress0Not started0Scope925 Jun 2026Complete9In progress0Not started0Scope92 Jul 2026Complete9In progress0Not started0Scope99 Jul 2026Complete9In progress0Not started0Scope916 Jul 2026Complete9In progress0Not started0Scope923 Jul 2026Complete9In progress0Not started0Scope930 Jul 2026Complete9In progress0Not started0Scope96 Aug 2026Complete9In progress0Not started0Scope913 Aug 2026Complete9In progress0Not started0Scope9

All delivered.

Not in a workstream 0 of 3 complete

0102011 Jun 2026Complete0In progress0Not started3Scope318 Jun 2026Complete0In progress0Not started3Scope325 Jun 2026Complete0In progress0Not started3Scope32 Jul 2026Complete0In progress0Not started3Scope39 Jul 2026Complete0In progress0Not started3Scope316 Jul 2026Complete0In progress0Not started3Scope323 Jul 2026Complete0In progress0Not started3Scope330 Jul 2026Complete0In progress0Not started3Scope36 Aug 2026Complete0In progress0Not started3Scope313 Aug 2026Complete0In progress0Not started3Scope3
  • Towpath signage

Needs attention · 1